Enaon EDA, as the distribution network operator in the area of Attica, may provide to Distribution Users and/or Final Consumers, indicatively and not restrictively, the following services which are ancillary to the Core Activity and which are provided exclusively within its Licence Area.
Please read more about the service you are interested in:
Connection of new Delivery Points to the Distribution Network | Cost of Service
(incl. VAT 24%) |
Connection of a new Delivery Point means the connection of a natural gas installation of a Final Consumer to the Distribution Network. | It is determined according to the respective tariff policy
the respective tariff policy ((see connection fees) |
In order to apply, click on the button below.
Meter capacity | Cost of Service* (incl. VAT 24%) |
G4 | 89,88 € |
G6 | 99,68 € |
G10 | 289,48 € |
G16 | 289,48 € |
G25 | 360,48 € |
PTZ volume corrector with telemetry system | 468,48 € |
* Cost includes the estimated price of the smart metering system metering unit to be installed, per meter type
In order to apply, click on the button below.
Technical inspections of pressure measuring and regulating stations at Delivery Points |
Cost of Service (incl.VAT 24%) |
Technical inspections of pressure measuring and regulating stations of the Delivery Points, with an internal consumption network operating pressure ≤ 25mbar. The Operator shall carry out a technical inspection of pressure measuring and regulating stations at Delivery Points at the request of the End User or the Final Consumer. | Charge ad hoc |
Technical inspections of pressure measuring and regulation stations at Delivery Points with an internal consumption network operating pressure > 25 mbar per consumption point. The Operator shall carry out a technical inspection of pressure measuring and regulating stations at Delivery Points at the request of the End User or the Final Consumer. | Charge ad hoc |
In order to apply, click on the button below.
Meter capacity | Cost of Service* (incl. VAT 24%) |
G4 | 89,88 € |
G6 | 99,68 € |
G10 | 289,48 € |
G16 | 289,48 € |
G25 | 360,48 € |
PTZ volume corrector with telemetry system | 468,48 € |
* Cost includes the estimated price of the smart metering system metering unit to be installed, per meter type
In order to apply, click on the button below.
Deactivation Cost | Cost of Service (incl. VAT 24%) |
Meter G4 to G40 (Deactivation following a request of the Distribution User upon request of the End Consumer) | 23,92 € |
Meter >G40 (Deactivation following a request of the Distribution User upon request of the End Consumer) | 32,51 € |
Meter G4 to G40 (Deactivation following a request of the Distribution User) | 24,24 € |
Meter >G40 (Deactivation following a request of the Distribution User) | 32,84 € |
Meter G4 to G40 (Deactivation on the Initiative of enaon EDA) | 28,81 € |
Meter >G40 (Deactivation on the Initiative of enaon EDA) | 37,40 € |
In order to apply, click on the button below.
Reactivation Cost | Cost of Service (incl. VAT 24%) |
Meter G4 to G40 (Reactivation following a request of the Distribution User upon request of the End Consumer) | 25,48 € |
Meter >G40 (Reactivation following a request of the Distribution User upon request of the End Consumer) | 34,08 € |
Meter G4 to G40 (Reactivation following a request of the Distribution User) | 25,48 € |
Meter >G40 (Reactivation following a request of the Distribution User) | 34,08 € |
Meter G4 to G40 (Reactivation following cut-off on the Initiative of enaon EDA) | 25,48 € |
Meter >G40 (Reactivation following cut-off on the Initiative of enaon EDA) | 34,08 € |
In order to apply, click on the button below.
Disconnection Cost | Cost of Service (incl. VAT 24%) |
• Sealing of the valve before the reducer
• Sealing of the valve before the reducer and removal of the reducer |
43,53 €
|
Shutting off the Buried GRM Valve | 43,18 € |
Also, if during the execution of Disconnection of the Supply with Intervention in the External Installation the Modification of the External Installation is required, the service in question will be charged on a case-by-case (ad hoc) basis
In order to apply, click on the button below.
Reconnection Cost | Cost of Service (incl. VAT 24%) |
•Reconnection following disconnection through valve sealing before the reducer •Reconnection following disconnection through valve sealing before the reducer and reducer removal |
35,22 €
|
Reconnection opening the Buried GRM Valve | 34,87 € |
In order to apply, click on the button below.
Conventional Meter Type | Cost of Service (incl. VAT 24%) |
G4 | 48,48 € |
G6 | 48,48 € |
G10 | 85,48 € |
G16 | 125,48 € |
G25 | 125,48 € |
G40 | 125,48 € |
G65 (Diaph) | 134,08 € |
G65 (T/R) | 234,08 € |
G100 (T) | 244,08 € |
G100 (R) | 259,08 € |
G160 | 284,08 € |
G250 | 334,08 € |
G400 | 384,08 € |
G650 | 434,08 € |
G1000 | 584,08 € |
G1600 | 693,84 € |
G2500 | 2.062,88 € |
Smart Meter Type | Cost of Service (incl. VAT 24%) |
G4 | 245,48 € |
G6 | 255,48 € |
G10 | 265,48 € |
G16 | 275,48 € |
G25 | 345,48 € |
In order to apply, click on the button below.
Recording of measurements at the request of the Final Consumer or End User with a frequency deviating from that specified by the Operator. | Cost of Service (incl. VAT 24%) |
Inspection of the meter in order to record the indication of the volume of Natural Gas supplied to the consumer. | Free of charge |
In order to apply, click on the button below.
Issuance of a Fire Safety Certificate | Cost of Service (incl. VAT 24%) |
Certificate of Occupancy for the Fire Department regarding the new gas uses of the commercial space. This certificate is necessary for the issuance of a license to operate the business premises. | Free of charge |
In order to apply, click on the button below.
Request the service you are interested in
Please fill in the form below with your details and the ancillary service you wish to apply for: